Equipment installed on this project



Alhaurín el Grande: Domusa Biomax Pellet Biomass Boiler Installation
Case Study: Complete Renewable Heating System — Oil Boiler Replaced with Premium Biomass Pellet Technology in the Guadalhorce Valley
62%
Fuel Savings
98.7%
Efficiency
94%
CO₂ Reduction
25kW
Output
Location
Alhaurín el Grande, Málaga Province, Spain
Property Type
Traditional Spanish Cortijo / Villa (280m²)
Previous System
Aging gasoil (oil) boiler — 18 years old, 78% efficiency
New System
Domusa Biomax 25kW biomass pellet boiler + 500L buffer accumulator
Total Capacity
25kW heating output — fully automated pellet feed
Installation Date
Completed March 2026
The Challenge
The owners of this traditional cortijo in Alhaurín el Grande faced escalating heating bills and an aging oil boiler that was beyond economical repair:
Our Renewable Heating Solution
Agua Therm's engineering team specified and installed a complete biomass heating system designed for the specific demands of a 280m² cortijo in the Málaga climate — providing year-round hot water and radiant-floor heating with fully automated pellet combustion:
Domusa Biomax 25kW Pellet Boiler
Spanish-engineered premium pellet boiler with 98.7% seasonal efficiency (EN303-5 certified). Lambda probe combustion control for automatic air-fuel optimisation. Ecodesign 2022 compliant — Class 5 emissions, one of the cleanest solid fuel appliances available.
500L Stainless Steel Buffer Accumulator
Thermal store installed in dedicated outdoor plant cabinet. Allows the boiler to run at optimum efficiency in long cycles, eliminating short-cycling, storing surplus heat for on-demand distribution. Extends boiler lifespan by 40–50%.
Dual Flue System — Double-Wall Insulated
Stainless steel insulated flue pipe installed through the existing structure. Maintains flue gas temperature above dew point, preventing condensation and corrosion. Compliant with Spanish CTE-HS3 building regulations.
Dedicated Electrical Distribution Upgrade
New consumer unit with MCB and RCD protection for all biomass system circuits: boiler, pump stations, controls, and buffer tank sensor wiring. Installed to IEC 60364 / REBT 2002 Spanish electrical safety standards.
Full specifications for the Domusa Biomax biomass pellet heating installation at this Alhaurín el Grande property:
Domusa Biomax Pellet Boiler
Buffer Accumulator & Flue System
Electrical Installation
Fuel Cost Comparison — Oil vs Biomass Pellets
Based on actual monitored fuel consumption from the first full heating season (winter 2025/2026) at this 280m² Alhaurín el Grande cortijo:
280m² cortijo with radiant floor heating and domestic hot water. Alhaurín el Grande climate (annual degree days: ~800 HDD). Gasoil price at CORES October 2025 reference rate. EN Plus A1 pellets from Guadalhorce Valley supplier.
| System | kWh/month | Cost/month | Annual Cost |
|---|---|---|---|
| Previous: Gasoil boiler (18yr, 78% efficiency) | ~2,800 kWh heat | €262 | €3,140 |
| New: Domusa Biomax pellets (98.7% efficiency) | ~2,800 kWh heat | €72 | €864 |
€190
Monthly Savings
€2,276
Annual Savings
72%
Cost Reduction
6–7 years
Payback Period
Gasoil price reference: CORES Spain (Corporación de Reservas Estratégicas de Productos Petrolíferos). EN Plus A1 pellet prices from Guadalhorce Valley supplier network. View source
Professional Installation Details
Agua Therm's certified technicians completed this full biomass heating installation over 4 days, including all associated pipework, flue, electrical, and commissioning:

Rob Greeves
Lead Installation Engineer, Agua Therm
Installation Lead — Rob Greeves, Agua Therm
"Rural properties off the gas grid have historically had no good options — oil was expensive and getting worse, LPG was marginal. The Domusa Biomax changes that equation completely. We sized this system carefully: 25kW matches the cortijo's heat loss calculation, and with the 500L buffer we get long burn cycles at 80-85% rated output rather than the constant stop-start that destroys efficiency in undersized installations. The Grundfos MAGNA3 variable-speed pump stations are key — they modulate to match demand across both heating circuits rather than running at full flow constantly. It's the kind of detail that separates a professionally designed installation from a simple boiler swap."

Craig Whitham
Electrical Systems Engineer, Agua Therm
Electrical Systems — Craig Whitham, Agua Therm
"The electrical upgrade was non-negotiable on this project — the existing board was a 1980s unit with no RCD protection and undersized circuits for the boiler and pump stations. We installed a dedicated dual consumer unit: one panel for the main home circuits and a completely separate board for all biomass system loads. Every biomass circuit has its own MCB and RCD rated to IEC 60364 / REBT 2002. The Domusa iConnect controller needs a clean, protected supply — so we ran a dedicated circuit for that too. This electrical work future-proofs the property and, crucially, keeps the home insurer satisfied."
Client Feedback
"We'd been putting off replacing the old oil boiler for years because we didn't know there was a proper alternative without connecting to gas — which isn't even available here in Alhaurín. Ben and the Agua Therm team explained biomass in a way that finally made sense. The Domusa boiler has been completely trouble-free since day one. We just top up the pellets every 3-4 weeks, the iConnect app handles everything else. This winter our heating bills dropped from about €260 a month to €70. That's real money back in our pocket every month. The installation was quick, clean and professional — they were done in 4 days and left the house spotless."
Property Owner
Alhaurín el Grande, Málaga
Verified Efficiency & Environmental Data
The performance data for this Domusa Biomax installation is backed by certified testing data and official Spanish and EU regulatory sources:
Domusa Biomax seasonal efficiency: 98.7%
Certified under EN303-5:2012 standard for heating boilers. Compared to 78% for the replaced oil boiler — a 20.7 percentage-point improvement in thermal conversion.
Wood pellets: ~0.055 €/kWh delivered — oil: ~0.135 €/kWh
EN Plus A1 certified pellets available from multiple Guadalhorce Valley suppliers. Gasoil at current Spanish pump prices (Oct 2025 CORES reference). 2.5x lower fuel cost per kWh of heat.
Biomass is carbon-neutral under EU Renewable Energy Directive
EN Plus A1 certified pellets are made from sustainably sourced wood residue. CO₂ absorbed during tree growth offsets CO₂ released during combustion — net lifecycle emissions ≈ 15–25g CO₂/kWh vs 270–290g CO₂/kWh for gasoil.
Buffer accumulator extends boiler efficiency by 8–12%
A 500L buffer prevents short-cycling (the main cause of efficiency loss in solid fuel boilers). Long burn cycles at rated output maintain combustion temperature and Lambda coefficient within optimal range.
Ecodesign 2022 Class 5 — lowest particulate emissions category
EU Ecodesign Regulation (EU) 2015/1189 sets strict limits on particulate matter, OGC, CO, and NOx. Class 5 (the highest) requires PM ≤ 40mg/m³. The Domusa Biomax achieves PM < 20mg/m³.
Biomass heating in Spain qualifies as renewable energy under IDAE Programa ERNCTE and the Junta de Andalucía EMPLE programme. Subsidy applications are managed by independent specialist companies — see agua-therm.com/heat-pump-subsidies-spain-2026 for verified specialists.
Location: Alhaurín el Grande, Guadalhorce Valley, Málaga
This biomass boiler installation was completed in Alhaurín el Grande, in the Guadalhorce Valley. Agua Therm installs pellet boilers and renewable heating systems across Málaga Province: Alhaurín de la Torre, Coín, Cártama, Álora, Pizarra, and inland towns.
Frequently Asked Questions — Biomass Boilers in Alhaurín el Grande
Is Biomass the Right Solution for Your Property?
If your property in Alhaurín el Grande, Coín, Mijas, or anywhere in Málaga Province is on oil or propane heating with no gas grid access, a biomass pellet boiler could cut your fuel bills by 50–65%. Contact Agua Therm for a free site assessment and system specification.
Also see
About the Author

Ben Hayden
English-Speaking Electrician & Independent Energy Advisor
Ben Hayden is an English speaking electrician and independent energy advisor based in Marbella, Spain, with over 15 years of electrical experience across Europe. He provides independent energy and electrical checks for overseas property owners and managers across the Costa del Sol — helping clients cut electricity bills, navigate Spanish regulations, and make confident decisions on solar PV, heat pump, EV charger and battery storage projects.
Ben advises in plain English on projects where the paperwork is in Spanish and the stakes are high. His writing has appeared in ExpatArrivals, The Olive Press, Euro Weekly News, BuildingTalk and pv magazine.